Priority
- Question it answers
- How much does the business want it?
- How it is set
- Task force input at the workshop: A, B or C
- Points
- A = 3, B = 2, C = 1
I led the diagnosis, executive alignment and roadmap for a company-wide digital transformation at an HR and staffing company in Iberia. About 60 initiatives, 6 workstreams and a 14-week planning cycle, sequenced with a weighted scoring model I designed with my team.
How I prioritised about 60 requests, how I ran delivery, and the work beyond the digital roadmap.
Every area asked for its own initiatives. I designed, with my team, a scoring model that let us say "this before that" with a number behind it. Priority and difficulty came from the task force at the workshop. I then used the scores, with my manager, to sequence the roadmap.
Each initiative gets a score from three questions: how much the business wants it, how easy it is, and how much it moves the company. The higher the total, the stronger the case for doing it early.
Final score formula: Priority plus Ease plus Impact equals Final score.
(difficulty, scored the other way round)
1 point each (8)
0.5 point each (3)
Top of the ranking
18 points:
ERP replacement
Its impact alone was 14: the impact scale is not capped at 10, so an initiative that enables many levers across several areas can score above it.
Bottom of the ranking
5 points:
Client-portal video tutorial
Same three inputs, same grid, same arithmetic.
58 initiatives, one scale, from 5 to 18. Priority and difficulty came from the task force; I did not set them.
| Cut | Result |
|---|---|
| Priority | 37 A, 11 B, 10 C |
| Difficulty | 35 rated easy (1.5 or less), 8 rated complex (3) |
| Breadth | 47 affect more than one area, 11 a single area |
The final deck showed every initiative on two axes. Here is how the groups fall out.
Quick wins
High impact, easy
Major projects
High impact, complex
Thankless tasks
Low impact, complex
Fill-ins
Low impact, easy
The roadmap showed each initiative's score next to its start quarter. 12 of the 17 initiatives scoring 12 or more were scheduled to start in 2022, 8 of them in the Q2 2022 first wave. The other 5 were scheduled for 2023–2024, for example the CRM in Q2 2023. So the score shaped the sequence without strictly dictating it.
It is transparent (every score traces back to ticked boxes in a grid), reproducible (a new request can be scored the same way) and easy to defend to executives ("why this before that?").
For each initiative I defined scope, objectives, expected results and resources, planned the stages, managed execution with clients, vendors, developers and marketing, monitored progress and closed with a final review.
Product thinking: the client communication tracker started as a shared spreadsheet to track process status with clients and became an app in the client portal that notifies clients of every status change, like parcel tracking.